All wiring and electrical boxes installed for wall outlets switches and light fixtures.
Install floors before drywall.
Drywall is installed finished a primed before flooring is installed so that the flooring isn t damaged during the drywall installation and finishing process.
Similarly it is asked do you install flooring before drywall.
In fact the subfloor is one of the first features of construction whereas drywall installation takes place toward the end of the project.
The key to solve this problem is to check the fit before you press the drywall tight to the wall.
After carefully measuring and cutting out the openings in your sheet of drywall hold the drywall in place.
When in doubt follow gravity.
Here s a checklist of items that need to be installed before the drywall goes up.
Let all the paint and primer splatters and globs of taping compound fall on the subfloor where they just have to be scraped up and call it good.
After floors this would be a huge pain to do since you would need to pull the door out and saw the jamb.
Allow the joint compound to dry until it s white or according to the.
Drain lines along with hot and cold water lines.
Also maybe others are more careful but i found it s hard not to ding the floor a little bit when doing doors afterwards.
If time is of the essence it s quicker to hang the drywall and tape out the walls first.
If the fit is close fasten the sheet with a few screws along the top edge or well away from the outlet openings.
We install and finish our walls and ceilings and paint a primer and first finish coat before doing any flooring.
Even the door trim should be in already just undercut it for the tile.
All that should be left when the tile floor goes in is to install the wood base.
Construction s a messy job and if you install the flooring first you ll spend more time on the walls because you ll have to be more careful not to drip joint compound on a new floor.
In standard home construction the contractor installs the subfloor before installing the drywall.
If time is a factor use fast drying joint compound.
Use a drywall knife to fill the large gaps with ready mixed joint compound.
The general construction rule is to work from the top of the room downward.